Agenda Item AGENDA STAFF REPORT ASR
Control 23-001065 |
||
MEETING
DATE: |
12/19/23 |
|
legal entity taking action: |
Board
of Supervisors |
|
board of supervisors district(s): |
2 |
|
SUBMITTING Agency/Department: |
Sheriff-Coroner (Approved) |
|
Department contact person(s): |
Brian
Wayt (714) 647-1803 |
|
|
Dave
O'Connell (714) 935-6844 |
|
Subject: Approve Amendment No. 2 to Archico
Design Build Inc. Agreement
ceo CONCUR |
County Counsel Review |
Clerk of the Board |
||||||||
Concur |
Approved
Agreement to Form |
Discussion |
||||||||
|
|
4/5
Vote |
||||||||
|
|
|
||||||||
Budgeted: Yes |
Current Year
Cost: $880,408 |
Annual Cost: N/A |
||||||||
|
|
|
||||||||
Staffing Impact: |
No |
# of Positions: |
Sole Source: N/A |
|||||||
Current Fiscal Year Revenue: N/A
|
||||||||||
Prior Board Action: 4/27/2021 #13, 12/14/2021 #14 |
||||||||||
RECOMMENDED
ACTION(S):
1. |
Approve
Amendment No. 2 to agreement with Archico Design Build Inc. for an equitable
adjustment for extended overhead for additional construction services and
costs due to unforeseen conditions found during demolition, excavation, and
construction, as part of the Katella Range Facility Upgrade Project at the
Sandra Hutchens Regional Law Enforcement Training Center in the not to exceed
amount of $880,408, for a revised cumulative contract not to exceed amount of
$10,983,246. |
2. |
Authorize
Sheriff-Coroner Department's Director of Research and Development or
authorized designee to execute Amendment No. 2. |
SUMMARY:
Approval of Amendment No. 2 to the
agreement with Archico Design Build Inc. will allow the Sheriff-Coroner
Department to finalize the construction project and prepare for close out.
BACKGROUND
INFORMATION:
The Sheriff-Coroner Department's (Sheriff)
range facility was partially updated with target systems that were more
adaptive to firearms being used; however, further alterations were needed to
bring the entire range system up to date and within code compliance with
additional safety and environmental measures.
Included in the FY 2020-21 Budget was
partial funding of the Katella Range Facility Upgrades. In FY 2021-22 Budget, the remaining funding
was provided.
On April 27, 2021, the Board of
Supervisors (Board) approved Sheriff's recommendation to award the Katella
Range Facility Upgrade Project contract to Archico Design Build Inc. effective
upon the receipt of all necessary signatures, bonds and insurance, in the not
to exceed amount of $7,146,000. The Notice
to Proceed was issued May 18, 2021.
Sheriff subsequently executed twenty-five
Change Orders under delegated authority pursuant to the County’s Design and
Construction Procurement Policy Manual.
List of Executed Change Orders
2021 |
2022 |
2023 |
5/13- $5.866 |
2/11 - $140.257 |
1/18 – 207.786 |
5/18 - $6.716 |
3/25 - $107.115 |
5/9 - $138.596 |
7/7 - $$7.934 |
4/6 - $94.563 |
5/15 - $134.479 |
8/19 -$152.352 |
4/8 - $38.324 |
7/10 - $163.446 |
8/24 - $199.809 |
5/20 - $206.975 |
8/31 - $44.188 |
9/14 - $92.231 |
5/25 - $9.458 |
- |
10/5 - $4.815 |
6/7 - $106.434 |
- |
11/1 - $108.904 |
6/21 - $86.795 |
- |
12/10 - $91.757 |
7/14 - $171.197 |
- |
- |
8/31 - $165.409 |
- |
- |
12/6 - $197.880 |
- |
Separately, on December 14, 2021, the
Board approved Amendment No. 1 to the agreement in the amount of $273,552.
These changes were necessitated by unforeseen conditions found within the scope
of work during the course of demolition, excavation, and construction. These
changes resulted in the initial date of completion being extended by 460 days
with a completion date of August 21, 2023.
As a result of the agreement’s
modifications, the Contractor made two requests for an equitable adjustment to
be made for extended overhead and operating costs, pursuant to the
agreement. See Attachment B. The
Contractor’s first request, Request for Change (RFC) RFC 116, was received February 28, 2023, for the time period
between June 1, 2022, and January 31, 2023, and was in the amount of $550,474.
The Contractor’s second request for extended overheard was received on
September 26, 2023, and was for the time period between February 1, 2023, and
August 21, 2023, in the amount of $407,147. The Contractor’s total request for
an equitable adjustment was $957,621.
Pursuant to Section 20 of the Agreement’s
General Conditions, if the County makes changes to the specifications or scope
of work that increase the cost of the project or extend the time for
performance, an equitable adjustment shall be made and the Agreement shall be
modified in writing. After a review of the Contractor’s requests and the monies
already paid to Contractor through the various change orders, Contractor agreed
that the amount for equitable adjustment is $880,408. Sheriff requests Board
approval to execute Amendment No. 2 to increase the agreement by $880,408 to
account for the Contractor’s extended overhead and operational costs due to the
project’s increased cost and extended timeframe.
Approval of the proposed Amendment No. 2
exceeds the thresholds allowed by Section 4.5- (1)c of the Design and
Construction Procurement Policy Manual and adds extended overhead to the
original project. Public Contract Code (PCC) Sections 20135 requires that the
changes in specifications contemplated within Amendment No. 2 are approved by a
2/3 vote of the members of the Board. Separately, PCC Section 20137 requires
that the changes in amount to the agreement are approved by a 4/5 vote of the
Board. See Attachments A and B for information regarding the amended changes.
This agreement includes subcontractors.
Contractor performance has been confirmed as at least satisfactory. Sheriff has
verified that there are no concerns that must be addressed with respect to
contractor's ownership/name, litigation status or conflicts with County
interests. There is no redline attached
as proposed Amendment No. 2 contains all of the information being revised.
Compliance
with CEQA:
This action is not a project within the
meaning of the California Environmental Quality Act (CEQA) Guidelines Section
15378 and is therefore not subject to CEQA, since it does not have the
potential for resulting in either a direct or physical change in the
environment, or a reasonably foreseeable indirect physical change in the
environment. The approval of this agenda item does not commit the County to a
definite course of action in regard to a project since it involves
authorization to amend the original awarded contract for the Katella Range
Facility Upgrade Capital Project. This proposed activity is therefore not
subject to CEQA. Any future action connected to this approval that constitutes
a change in project scope will be reviewed for compliance with CEQA.
FINANCIAL
IMPACT:
Appropriations for this Amendment
are included in Budget Control 060, Sheriff Coroner’s FY 2023-24 Budget. The Amendment contains language for the
agreement between the contractor with the County that final payment and release
retention will follow the filing of the Project's Notice of Completion within
fifteen (15) days after the date of completion of the punch list.
STAFFING
IMPACT:
N/A
ATTACHMENT(S):
Attachment
A - Amendment No. 2 to Agreement MA-060-21011194
Attachment B – Request For Change 116 Extended Overhead and request dated
September 26, 2023
Attachment C – Change Submittal and Summary
Attachment D – Public Contract Codes 20135 and 20137