Agenda Item
ASR
Control 23-000644 |
||
MEETING
DATE: |
09/26/23 |
|
legal entity taking action: |
Board
of Supervisors and Orange County Flood Control District |
|
board of supervisors district(s): |
1 |
|
SUBMITTING Agency/Department: |
OC
Public Works (Approved) |
|
Department contact person(s): |
Fiona
Man (714) 647-3953 |
|
|
Melissa
Pasa (714) 647-3977 |
|
Subject: Approve Cooperative Agreement for
East Garden Grove-Wintersburg Channel Bridges
ceo CONCUR |
County Counsel Review |
Clerk of the Board |
||||||||
Concur |
Approved
Agreement to Form |
Consent
Calendar |
||||||||
|
|
3
Votes Board Majority |
||||||||
|
|
|
||||||||
Budgeted: N/A |
Current Year
Cost: N/A |
Annual Cost: N/A |
||||||||
|
|
|
||||||||
Staffing Impact: |
No |
# of Positions: |
Sole Source: N/A |
|||||||
Current Fiscal Year Revenue: N/A
|
||||||||||
Prior Board Action: 6/6/2023 #11, 11/8/2022 #23,
5/21/2013 #45 |
||||||||||
RECOMMENDED
ACTION(S):
1. |
Approve
Cooperative Agreement between the Orange County Flood Control District and
the City of Huntington Beach for Funding, Construction and Maintenance of the
East Garden Grove-Wintersburg Channel (C05) Bridges Project at Warner Avenue,
Springdale Street and Edwards Street Improvements Project, effective upon
Board of Supervisors approval. |
2. |
Authorize the
Director of OC Public Works or designee to execute future amendments to the
Cooperative Agreement, provided those amendments would result in minor, non-substantive
changes that do not create or increase a financial obligation on the part of
the County of Orange or the Orange County Flood Control District. |
SUMMARY:
Approval of the Cooperative
Agreement with the City of Huntington Beach for construction and
post-construction maintenance responsibilities of the East Garden
Grove-Wintersburg Channel (C05) Bridges Project will allow the Orange County
Flood Control District to complete the work necessary to provide greater flood
protection for the residents of the County of Orange.
BACKGROUND
INFORMATION:
The East Garden Grove-Wintersburg
Channel (C05) Bridges Project (Project) is located at the Warner Avenue,
Springdale Street and Edwards Street bridge crossings (Bridges) of the Orange
County Flood Control District’s (District) East Garden Grove-Wintersburg
Channel (Channel) in the City of Huntington Beach (City). See Attachment B for
the Project Location Map.
The Project is located within the
Westminster Watershed, the largest remaining floodplain in Orange County. To
ultimately remove the adjacent residences from the floodplain, the District has
programmed a series of Channel improvement projects from Pacific Coast Highway
to the San Diego Freeway, Interstate 405. In April 2023, the District completed
flood control improvements along this segment of the Channel from Warner Avenue
to 1,200 feet downstream of Goldenwest Street to increase the Channel capacity
and fortify the levees.
The District identified that the
three City-owned and maintained Bridges do not meet Federal Emergency
Management Agency freeboard requirements and, therefore, require the
installation of flood walls. OC Public Works has coordinated with the City for
this subsequent Project to address flood control deficiencies identified by
installing flood walls on both the upstream and downstream ends of the Bridges
and replacing the Bridge decks to be compatible with the recently constructed
Channel improvements to comply with federal flood protection requirements.
On November 8, 2022, the Board of
Supervisors (Board) approved the Construction Manager At-Risk design phase
services contract, MA-080-23010108, with Myers & Sons Construction, LLC and
authorized the expenditure and execution of the negotiated construction phase
services Contract MA-080-23010112 in an amount not to exceed $18.233 million
for the Project.
The proposed Cooperative Agreement
MA-080-23011516 (Cooperative Agreement) between the District and the City
clarifies construction and post-construction maintenance responsibilities for
the Project. The District is implementing the flood control improvements
necessary to meet federal flood protection requirements and the City will
maintain ownership and maintenance of the Bridges upon Project completion. On
June 20, 2023, the City Council approved the Cooperative Agreement provided as
Attachment A herein.
OC Public Works recommends the
Board approve the Cooperative Agreement between the District and the City for
the Project to complete the work necessary to provide greater flood protection
for the residents of Orange County.
The Project is included in the OC
Public Works 7-Year Capital Improvement Program (CIP) FY 2023-24 through FY
2029-30 adopted by the Board on June 6, 2023. OC Flood CIP, Fund 401, will be
utilized to fund the construction of the flood control improvements and ongoing
maintenance costs of the Bridges will be the responsibility of the City.
General
Plan: The
Project is consistent with the City’s General Plan.
Compliance
with CEQA:
This Project is a necessarily included element of the Project considered in
Final Mitigated Negative Declaration (MND) IP No. 11-144, approved by the Board
on May 21, 2013, and the OC Public Works OC Engineering Countywide Routine
Maintenance Manual (October 2012) included as part of Initial Study/MND IP No.
11-444, which adequately addressed the effects of the proposed Project. No
substantial changes have been made in the Project, no substantial changes have
occurred in the circumstances under which the Project is being undertaken and
no new information of substantial importance to the Project, which was not
known or could not have been known when the Final MND IP No. 11-144 was
approved has become known; therefore no further environmental review is
required. The City will be the CEQA lead agency for maintenance once the Project
is complete.
FINANCIAL
IMPACT:
There is no financial impact
associated with the recommended actions of this Agenda Staff Report.
In the event District or City defaults in
the performance of any of their obligations under this Cooperative Agreement or
materially breaches any of the provisions of this Cooperative Agreement, the
City and the District shall have the option to terminate this Cooperative
Agreement upon thirty days' prior written notice to the other party. In the
event the City or the District cures such default within the thirty-day notice
period, the City and District selection to terminate shall be deemed revoked
and of no further force and effect as to that particular default. Any party's
failure to enforce this Cooperative Agreement as to one instance of breach
shall not constitute a waiver of any party's ability to enforce this
Cooperative Agreement as to any future breaches or noncompliance.
STAFFING
IMPACT:
N/A
ATTACHMENT(S):
Attachment
A - Cooperative Agreement MA-080-23011516
Attachment B - Project Location Map