Agenda Item
ASR
Control 25-000434 |
||
|
MEETING
DATE: |
09/23/25 |
|
|
legal entity taking action: |
Board
of Supervisors |
|
|
board of supervisors district(s): |
5 |
|
|
SUBMITTING Agency/Department: |
John
Wayne Airport (Approved) |
|
|
Department contact person(s): |
Charlene
Reynolds (949) 252-5183 |
|
|
|
Komal
Kumar (949) 252-5166 |
|
Subject: Award Contract for Construction
Services with Swinerton Builders
|
ceo CONCUR |
County Counsel Review |
Clerk of the Board |
||||||||
|
Concur |
Approved
Agreement to Form |
Discussion |
||||||||
|
|
|
3
Votes Board Majority |
||||||||
|
|
|
|
||||||||
|
Budgeted: Yes |
Current Year
Cost: $6,741,028 |
Annual Cost: FY 2026-27 $30,542,683 |
||||||||
|
|
|
|
||||||||
|
Staffing Impact: |
No |
# of Positions: |
Sole Source: No |
|||||||
|
Current Fiscal Year Revenue: N/A
|
||||||||||
|
Prior Board Action: 12/19/2023 #21 |
||||||||||
RECOMMENDED
ACTION(S):
|
1. |
Find that the Project is Categorically
Exempt from the California Environmental Quality Act (CEQA), Class 2
(Replacement or Reconstruction) pursuant to CEQA Guidelines Section 15302. |
|
2. |
Award a contract to Swinerton Builders
for Construction Services to provide Airport Power Generation and
Distribution Upgrades Phase 1, effective upon execution of all necessary
signatures, to be completed within 1022 days of the effective date of the Notice
to Proceed for a Total Contract Price of $54,453,355. |
|
3. |
Authorize the Airport Director or
designee to execute the contract with Swinerton Builders. |
SUMMARY:
Award of the contract to Swinerton
Builders for Phase 1 of the John Wayne Airport Power Generation and
Distribution Upgrades Project will provide for the replacement of the aging
main terminal medium-voltage switchgear and five unit substations to support
long-term operational efficiency and system reliability.
BACKGROUND
INFORMATION:
John Wayne Airport (JWA) is Orange
County's only commercial airport. Serving over three million people across 34
cities, JWA served over 11 million passengers in 2024.
A prior condition and resiliency
assessment identified concerns and deficiencies associated with JWA's
electrical distribution system, referred to as the Power Distribution Program
(PDP). The current project is the first phase of implementation of the PDP, and
focuses on upgrades to the terminal electrical distribution system and the
proactive replacement of aging infrastructure.
The Airport Power Generation and
Distribution Upgrades Phase 1 (Project) proposes to replace the aging main
terminal medium-voltage switchgear and the five unit substations – one in
Terminal A, two in Terminal B, one in Parking A2, and one in Parking B2, which
have over 20 years of use and are nearing the end of their design life. The
terminals' 12-kilovolt electrical distribution systems will be re-fed from the
new switchgear to the unit substations. Additionally, the Project includes
upgrades to the existing emergency power systems, including the replacement of
outdated Automatic Transfer Switches (ATS) in Terminals A and B.
On December 19, 2023, the Board of
Supervisors (Board) selected Swinerton Builders for Construction Manager at
Risk (CMAR) Services for the Project, in an amount not to exceed $14,194,585.
This total includes Pre-Construction Services valued at $1,794,585 and long
lead item early procurement valued at $12,400,000.
JWA is now recommending that the
Board award Contract MA-280-25011401 (Contract) to Swinerton Builders for
Construction Services for the Project, effective upon execution of all
necessary signatures, to be completed within 1022 days of the effective date of
the Notice to Proceed, for a Guaranteed Maximum Price (GMP) of $54,453,355.
JWA procured Services for this
Project in accordance with the 2020 Design and Construction Procurement Policy
Manual (DCPM), Section 5.6. The Orange County Preference Policy is not
applicable to contracts procured in accordance with the DCPM.
The Contractor's license number was
verified as current and active through the California Contractors State License
Board database on April 3, 2025. A copy of the verification is on file. The
Contractor is based in Contra Costa County.
JWA has conducted due diligence on
the Contractor. Reference checks were satisfactory and completed with SC
Consulting, Paslay Group, and Long Beach Airport regarding similar projects.
An analysis was completed to verify
whether the Contract provides the county with persons specially trained,
experienced, expert, and competent to perform special services in accordance
with the law.
This Contract includes
subcontractors. See Attachment B for information regarding subcontractors and
Contract Summary Form.
Compliance
with CEQA:
The proposed Project is Categorically Exempt (Class 2) from the provisions of
CEQA pursuant to CEQA Guidelines Section 15302, because it provides for the
replacement or reconstruction of existing utility systems or facilities
involving negligible or no expansion of capacity.
FINANCIAL
IMPACT:
Appropriations for this Contract
are included in Fund 281, Airport Construction Fund, FY 2025-26 Budget and will
be included in the budgeting process for future years.
The proposed contract is contingent
upon funding availability. In the event funding is reduced or terminated, the
County may renegotiate the level of services and/or terminate the contract, as
necessary
STAFFING
IMPACT:
N/A
ATTACHMENT(S):
Attachment
A – Contract MA-280-25011401 with Swinerton Builders
Attachment B – Contract Summary Form