Agenda Item
ASR
Control 23-000837 |
||
MEETING
DATE: |
12/19/23 |
|
legal entity taking action: |
Board
of Supervisors |
|
board of supervisors district(s): |
5 |
|
SUBMITTING Agency/Department: |
OC
Public Works (Approved) |
|
Department contact person(s): |
James
Treadaway (714) 667-9700 |
|
|
Charlene
Reynolds (949) 252-5183 |
|
Subject: Approve Contract for Airport
Terminal Electrical Distribution Upgrades
ceo CONCUR |
County Counsel Review |
Clerk of the Board |
||||||||
Concur |
Approved
Agreement to Form |
Discussion |
||||||||
|
|
3
Votes Board Majority |
||||||||
|
|
|
||||||||
Budgeted: Yes |
Current Year
Cost: See Financial
Impact Section |
Annual Cost: N/A |
||||||||
|
|
|
||||||||
Staffing Impact: |
No |
# of Positions: |
Sole Source: No |
|||||||
Current Fiscal Year Revenue: N/A
|
||||||||||
Prior Board Action: N/A |
||||||||||
RECOMMENDED
ACTION(S):
1. |
Find that the project is categorically
exempt from CEQA, Class 1 (Existing Facilities) pursuant to CEQA Guidelines
Section 15301. |
2. |
Approve a contract with Swinerton
Builders to provide Pre-Construction Phase Services for the John Wayne
Airport Terminal Electrical Distribution Upgrades Project, for a Maximum Contract Price of $14,194,585, effective
upon execution of all necessary signatures. |
3. |
Authorize the Director of OC Public
Works or designee to execute the Pre-Construction Phase Services contract
with Swinerton Builders. |
SUMMARY:
Approval of the contract for
Pre-Construction Phase Services for the John Wayne Airport Terminal Electrical
Distribution Upgrades Project will modernize John Wayne Airport's Terminal
complex electrical distribution system, which includes replacing aging
switchgear and unit substations, providing provision for future microgrid/load
shedding controls and monitoring system and modifying emergency distribution
systems.
BACKGROUND
INFORMATION:
John Wayne Airport (JWA), located
approximately 35 miles south of Los Angeles, between the cities of Costa Mesa,
Irvine and Newport Beach, is owned and operated by the County of Orange
(County) and is the only commercial service airport in Orange County. JWA’s
service area includes more than three million people within the 34 cities and
unincorporated areas of Orange County. In 2022, approximately 11.3 million
passengers were served.
The proposed JWA Terminal
Electrical Distribution Upgrades Project (Project) proposes to replace the
aging main terminal medium-voltage switchgear and the five unit substations -
one in Terminal A, two in Terminal B, one in Parking A2 and one in Parking B2,
which have over 20 years of use and are ending their design life. The 12
kilovolt distribution for the terminals will be re-fed from the new switchgear
to the unit substations. In addition, the existing emergency systems will be
upgraded to replace old air traffic service (ATS) in Terminals A and B and to
separate emergency (life safety) loads from other loads per California
Electrical Code Article 700.5(D) in Terminal A, Terminal B, Parking A2 and
Parking B2, which currently have emergency power systems and ATS serving a
combination of emergency and standby loads
On April 4, 2023, OC Public Works
issued a Request for Proposal (RFP) for Construction Manager At- Risk
Pre-Construction Services (Services) the Project. The RFP was advertised in
several industry publications and on the County online bid system. One proposal
was received and deemed responsive.
The evaluation panel composed of members from OC Public Works scored the
responsive proposal. See Attachment C for Memorandum of Recommendation and
Evaluation Ranking Summary.
Contractors |
Rank |
Swinerton Builders |
1 |
OC Public Works is procuring
Services for this Project in accordance with the 2020 Design and Construction
Procurement Policy Manual (DCPM), Section 3. The Orange County Preference
Policy is not applicable to contracts procured in accordance with the DCPM.
OC Public Works is recommending the
Board of Supervisors (Board) approval of Contract MA-080-24010644 (Contract)
with Swinerton Builders (Contractor) for Services for the Project, for a
Maximum Contract Price of $14,194,585, which is composed of Guaranteed Maximum
Price (GMP) No. 1 for Pre-construction Services in the amount of $1,794,585 and
an allotment for additional GMP’s for procurement of long lead-time equipment
and additional site investigations, effective upon execution of all necessary
signatures. Upon substantial completion of the design by the Architect-Engineer
and negotiation of a GMP for construction services with the Contractor, OC
Public Works will return to the Board for award of the construction services
contract.
The Contractor's license number was
verified as current and active through the California Contractors State License
Board database on May 26, 2023. A copy of the verification is on file. The
Contractor is based in Contra Costa County.
An analysis was conducted to
determine the cost/benefit of contracting out versus providing Services
in-house. Based on this analysis, OC Public Works has determined that
contracting for Services was required as the specialized engineering expertise
needed to complete the work is currently unavailable utilizing in-house staff.
OC Public Works has conducted due
diligence on the Contractor. Reference checks were satisfactory and completed
with SC Consulting, Paslay Group and Long Beach Airport regarding similar
Projects.
This Contract includes
subcontractors. See Attachment B for Contract Summary Form.
Compliance
with CEQA:
The proposed Project is Categorically Exempt (Class 1) from the provisions of
CEQA pursuant to CEQA Guidelines Section 15301, because the Project includes
maintenance and repair of a public facilities and mechanical equipment,
involving negligible expansion of the existing use.
FINANCIAL
IMPACT:
Appropriations for this Contract
are included in Fund 281, Airport Construction Fund, FY 2023-24 Budget and will
be included in the budgeting process for future years. The Contract will be
completed in phases and encumbered accordingly up to the Maximum Contract Price
of $14,194,585.
The proposed Contract includes a provision
stating the Contract may be terminated for convenience of the County upon less
than seven days written notice to the Contractor and upon 10 days written
notice to the Contractor prior to the effective date of the termination for
cause without penalty to the County.
STAFFING
IMPACT:
N/A
REVIEWING
AGENCIES:
John
Wayne Airport
ATTACHMENT(S):
Attachment
A - Contract MA-080-24010644 with Swinerton Builders
Attachment B - Contract Summary Form
Attachment C - Memorandum of Recommendation and Evaluation Ranking Summary
Attachment D - Summary of Evaluators' Scoring