Agenda Item
ASR
Control 24-000430 |
||
|
MEETING
DATE: |
06/25/24 |
|
|
legal entity taking action: |
Board
of Supervisors |
|
|
board of supervisors district(s): |
2 |
|
|
SUBMITTING Agency/Department: |
County
Executive Office (Approved) |
|
|
Department contact person(s): |
Michelle
Aguirre (714) 834-4304 |
|
|
|
Thomas
A. Miller (714) 834-6019 |
|
Subject: Ordinance
and Pre-Development Agreement for Workforce Reentry Center
|
ceo CONCUR |
County Counsel Review |
Clerk of the
Board |
||||||||
|
Concur |
Approved Ordinance to Form |
Public Hearing |
||||||||
|
|
|
3 Votes Board Majority |
||||||||
|
|
|
|
||||||||
|
Budgeted: N/A |
Current
Year Cost: N/A |
Annual
Cost: See Financial Impact Section |
||||||||
|
|
|
|
||||||||
|
Staffing
Impact:
|
No |
#
of Positions: |
Sole
Source: No |
|||||||
|
Current Fiscal Year Revenue: N/A
|
||||||||||
|
Prior Board Action: 2/27/2024 #43 |
||||||||||
RECOMMENDED
ACTION(S):
|
1. |
Read the title
of the Ordinance: An Ordinance of the County of Orange, California
authorizing contracts with Griffin/Swinerton LLC, Medlin Workforce &
Reentry Solutions LLC, and/or Hub for Integration, Reentry & Employment
for development and operation of a Workforce Reentry Center. |
|
2. |
Waive further
reading of the Ordinance. |
|
3. |
Conduct a Public Hearing. |
|
4. |
Consider the matter and adopt the
Ordinance. |
|
5. |
Approve
Pre-Development Agreement with Griffin/Swinerton LLC for Phase 1 services to
be completed within 18-month term, upon execution of agreement, including
refining site design and facility programming into a final site plan,
schematic design, design development, approvals/entitlements, and a
Guaranteed Maximum Price for the Workforce Reentry Center. |
|
6. |
Authorize the
Chief Real Estate Officer or designee to execute the Pre-Development
Agreement with Griffin/Swinerton LLC in substantially the same form attached
with minor modifications that do not change the obligations to the County
with approval by County Counsel, and to take any action necessary to
administer the Pre-Development Agreement within an amount not to exceed
$5,378,794, including executing future amendment(s) to the Pre-Development
Agreement provided those amendments would result in minor, non-substantive
changes which do not create or increase financial obligations or liabilities
on the part of the County by more than $75,000 annually, and return to the
Board of Supervisors for approval of future Development Agreement, lease
agreement, and/or management/operator agreement related to designing,
entitling, constructing, operating, and maintaining the Workforce Reentry
Center. |
SUMMARY:
Adoption of an
Ordinance will authorize contracts facilitating the development and operation
of the Workforce Reentry Center and approval of a Pre-Development Agreement
with Griffin/Swinerton LLC will provide preconstruction and design services for
the development of the Workforce Reentry Center.
BACKGROUND
INFORMATION:
On February 27,
2024, the Board of Supervisors (“Board”), pursuant to Government Code Sections
25515, et seq., adopted a Resolution
that approved a request for proposals process and selected the team made up of
Griffin/Swinerton LLC (Developer) and Medlin Workforce & Reentry Solutions
LLC (Operator) as the Primary Respondent to the County’s competitive
solicitation for development and operation of a Workforce Reentry Center
(Project) at 561 The City Drive South in Orange (Property). The Resolution also found that the Workforce
Reentry Center (WRC) will result in agency uses and is therefore not subject to
the Surplus Land Act. On this same date,
the Board also approved an Exclusive Negotiation Agreement (ENA) with Developer
and Operator that provided a period for the County, Developer and Operator
(collectively, the Parties) to develop programming and negotiate the form of a
subsequent agreement for the Project.
Conceptual Program
Since execution of
the ENA, the Parties have worked together to develop programming, a conceptual
site design (attached), and a preliminary Project budget. The preliminary building program for the WRC
is comprised of an approximately 36,000 square foot (SF), two-story
vocational/operations building, an approximately 16,000 SF, one-story
retail/culinary building, and an approximately 26,000 SF, two-story housing
building. The vocational/operations
building is anticipated to include a large training warehouse, multi-purpose
room, classrooms, and offices for operations and management. The retail/culinary building is anticipated
to include various kitchens for training and production, a grab-n-go style
café, and other retail space where program participants will develop, produce,
and provide goods and/or services to the public as part of the vocational
training program. The housing building
is anticipated to provide on-site housing for approximately 50 selected program
participants. The site is also conceptually
planned to include approximately 200 surface level parking spaces, an outdoor
pet training/relief area, an outdoor activity/garden area for program
participants, and a new security block wall between the Property and the
adjacent Theo Lacy Facility.
Pre-Development Agreement, Estimated Costs and Future
Contracts
The County and
Developer have also negotiated a Pre-Development Agreement (PDA). The attached PDA with Developer will provide
for preconstruction and design services including refinements to the site
design and facility programming into a final site plan, schematic designs,
design development, approvals/entitlements, and establishing a Guaranteed
Maximum Price (GMP) for the development (Phase 1). Once Phase 1 is completed, a negotiated Development
Agreement (DA) with final development plans and GMP will be presented to the
Board for approval. The subsequent DA
will provide for construction services including completion of construction
drawings and vertical development of the WRC (Phase 2). Based upon early conceptual estimates, the
overall estimated cost at this time for the development of the WRC is
approximately $86.4 million, excluding an escalation allowance and any costs
associated with County administration and County contingency. Phase 1 will cost approximately $5.4 million
and Phase 2 is estimated to cost approximately $81 million. A tentative schedule estimates Phase 1 will
be completed in May 2025 and Phase 2, if approved, will be completed in
September 2027. Developer and Operator
are part of a consortium also comprised of Hub for Integration, Reentry &
Employment, LPA Design Studios, Swinerton Builders, and Kidder Mathews. Any lease or management/operator agreement
with the Operator and/or Hub for Integration, Reentry & Employment, as
appropriate, will also be presented for Board approval at a future date.
The PDA includes
subcontractors and due to the nature of the services, could require additional
subcontractors. In order to add
subcontractors to the PDA, Developer must seek express written consent from
County. Should the addition of a
subcontractor impact the scope of work and/or contract amount, the item will be
brought back to the Board for approval.
See attached Contract Summary Form.
Contract Authorization and Ordinance
The solicitation
process and the applicable agreements are authorized by Government Code
Sections 25515, et seq., which finds
that provisions for residential, commercial, industrial, and cultural
development of public property owned by counties constitutes a valid public
purpose. Government Code Section 25515.1
permits counties to sell or lease to, or enter into a joint venture with, a
private entity any of its real property for these purposes. It also permits counties to participate as a
principal party in the development of these uses under certain circumstances or
to contract for management, operation, or leasing of its real property for
these same purposes. Pursuant to
Government Code Section 25515.2(a), any lease, development, or contract
agreement entered into pursuant to Government Code Sections 25515, et seq., shall be authorized by an
ordinance adopted by the Board.
Additionally, Government Code Section 25515.2(b) requires the Board to
hold a public hearing prior to adopting such an ordinance. The attached Ordinance makes certain findings
pursuant to Government Code Sections 25515, et seq., and authorizes contracts facilitating development and
operation of the WRC.
Compliance
with CEQA: This
action is not a project within the meaning of CEQA Guidelines Section 15378 and
therefore not subject to CEQA, since it does not have the potential for
resulting in either a direct physical change in the environment, or a
reasonably foreseeable indirect physical change in the environment. The approval of this agenda item does not
commit the County to a definite course of action in regard to a project since
it includes adoption of an ordinance and approval of a Pre-Development
Agreement to provide preconstruction and design services for a Workforce
Reentry Center. This proposed activity
is therefore not subject to CEQA. Any future action connected to this approval
that constitutes a project will be reviewed for compliance with CEQA. During the design of the Project, a separate
CEQA review will be completed.
General
Plan: The
WRC is consistent with the General Plan of City of Orange, pursuant to
Government Code Section 65402(b).
FINANCIAL IMPACT:
Phase 1 costs
shall not exceed $5,378,794 and will be paid as costs are incurred during the
term of the PDA, which term shall not exceed 18 months, unless mutually
extended by Developer and County via amendment.
Appropriations for Phase 1 will be included in Countywide Capital
Projects Non-General Fund 15D FY 2024-25 Budget, offset by equivalent transfers
in from OC CARES, Fund 12M, and will be included in the budgeting process for
future years, as applicable.
The PDA contains a
provision that the County may at any time, and without cause, terminate the PDA
in whole or in part, upon not less than 30 calendar days’ written notice to
Developer, without penalty.
STAFFING IMPACT:
N/A
ATTACHMENT(S):
Attachment A - Ordinance
Attachment B - Conceptual Site Plan
Attachment C - Pre-Development Agreement
Attachment D - Government Code Sections 25515, et seq.
Attachment E – Contract Summary Form